#### Geological and physical oceanography background of KM3Net sites
<imgsrc="./img/KM3Net_Location.png"width="800">
- The KM3NeT-Italy infrastructure is located at 36° 16′ N 16° 06′ E at a depth of `3500` m, about `100 km` offshore from Porto Palo di Capo Passero, Sicily, Italy. `ARCA`
- The KM3NeT-France infrastructure is located at 42° 48′ N 06° 02′ E at a depth of `2450` m, about `40 km` offshore from Toulon, France. `ORCA`
#### Configuration of KM3Net-ORCA Detector
<imgsrc="./img/ORCA_detector.png"width="800">
- KM3Net-Fr海底中微子望远镜规划由115串潜标阵列(DU)组成
- 每一个DU包括18个玻璃球(DOM)
- 每一个DOM内嵌31个光电倍增管(PMT)
- DU展开长度为200米,DOM间隔在8~10米之间
- DU之间间隔在20~23米之间
#### DU Configuration of KM3Net-ORCA Detector
<imgsrc="./img/KM3Net_DU_Unfold.png"width="800">
<imgsrc="./img/ORCA_DU_Fold.png"width="800">
<imgsrc="./img/ORCA_DOMs.png"width="800">
<imgsrc="./img/ORCA_DU.png"width="800">
The ensemble of the loaded LOM and anchor weighs approximately `26 kN`. In seawater the weight is approximately `5.5 kN`. The ensemble is lowered with a winch cable to the seafloor from a dedicated ship (figure 8). Positioning at the seafloor requires an acoustic positioning system with a transponder to the lowered ensemble. The required accuracy is about `±1 m`. Further assistance is needed from an ROV to connect the interlink to the sea-floor network, i.e. connect the VEOC backbone via the base module of the DU-string to the network to shore. After successful connection, of which the verification takes about 30 minutes, the winch cable is released acoustically. This verification entails a full test of the DU-string in furled position: powering on, and testing the communication with each optical module.
In principle, the ensemble could be hauled up again to the surface if the DU-string does not pass the verification test. To provide more freedom to the ship’s maneuvering and wave motion during the verification, a *`small buoy is attached a few tens of meters above the LOM`* to allow for slack in the winch cable without danger of entanglement or collision of the acoustic release with the sphere. Once the release mechanism described in section 4.5 is opened by the ROV pulling the rope near the seafloor the LOM moves upwards from its support structure at the anchor-frame and starts self-unrolling along the two Dyneema ropes.
After `10 sea-trials`, the first complete DU-string deployments were successfully launched with the complete unrolling of an ARCA DU-string up to 750 m long, the undamaged exiting of optical modules and backbone cable and the surfacing of the LOM.`Loading the LOM and deploying it to the seafloor are procedures that require training of dedicated teams. `
During a sea campaign performed last week, ORCA has been enlarged by means of `4 new detection units`.
The operation was performed with the Castor ship of Foselev, for deployment of the detection units, and with the Janus II of SAAS (formerly Comex), equipped with a deep-sea remotely operated vehicle, for submarine operations.
During a two days sea operation, 27-28 April 2023, `three detection units` were successfully connected to the ORCA detector of KM3NeT `in a record time of just over 24 hours`.
As usual, the operation was performed with two ships: the Castor of Foselev, for deployment of the detection units, and the Janus II of SAAS (formerly Comex), equipped with a deep-sea remotely operated vehicle, for submarine operations.